Engineering and approvals
System design, electrical protection and controls, ATS operating strategy, low-SOC recovery design and Energex technical coordination.
Turnkey EPC for a foldable solar and battery microgrid, integrating ATS-controlled supply, a grid charger and coordinated controls to address site grid-capacity constraints.

The site’s grid-capacity constraints called for an integrated solar and storage system. A foldable PV array and BESS supply site loads, with an ATS-interlocked utility interface and a grid charger for low-state-of-charge recovery.
System design, electrical protection and controls, ATS operating strategy, low-SOC recovery design and Energex technical coordination.
Equipment procurement, BESS and foldable solar installation, switchboard and grid-charger integration, AC/DC cabling and communication systems.
BESS, PCS, BMS and EMS commissioning, solar integration tests, ATS interlock checks, islanded load tests, grid-charger verification, as-built documentation and training.
Solar and BESS supply loads through an ATS-interlocked arrangement. The system supports islanded operation under BESS supply, automatic utility transfer when required, and low-SOC recovery through the 120kW grid charger.