← Back to projects
Engineering & AC-coupled integration

Solar and BESS integration.

Queensland, Australia

Engineering and AC-coupled integration of battery storage with an existing solar system, connecting protection, control and communication interfaces across the site’s electrical network.

Battery equipment at the Bowen Hills solar and BESS integration site

Project at a glance.

BESS power
1MW
Power conversion
2 × 500kW PCS
Integration
AC-coupled existing PV
System arrangement
Two independent BESS blocks
The setting

Project context.

The grid-connected design integrates battery storage with the site’s existing solar PV. Two independent battery blocks connect to a common AC network, supporting coordinated storage and solar operation.

Engineering & AC-coupled integration

Our scope.

01

Engineering and interfaces

BESS design, protection and control engineering, communication design and grid-interface coordination.

02

AC-coupled integration

Connect the BESS blocks with the existing solar system and AC network, including switchboard, cabling and communication interfaces.

03

Testing and handover scope

Integration testing, grid-connected charge/discharge testing, protection and control verification, and as-built and O&M documentation form the described delivery scope.

How it connects

System configuration.

Two blocks on a common network

Each 500kW PCS interfaces a battery group with the site’s AC system. BMS, PCS and EMS controls coordinate storage with existing PV, with protection and communication interfaces across the electrical network.

Continue exploring

Related experience.

Queensland, Australia

Off-grid hybrid integration

System integration
Your next project

Bring your requirements.
Define the next step.

Talk to our team about a similar system or specialist support.

All projects